Tank Construction Photo Gallery
Oct. 24, 2018 Crates with new tank being moved on site
Oct. 25, 2018 Morning
Oct. 25, 2018 Morning
Oct. 25, 2018 Midday
Oct. 25, 2018 Midday
Oct. 25, 2018 Midday
Oct. 26, 2018
Oct. 26, 2018
Oct. 27, 2018
Oct. 28, 2018 looking in the access hole
Oct. 28, 2018 Morning
Oct. 28. 2018 Morning two rows of panels done
Oct. 29, 2018 Morning third row of panels going on
Oct. 29, 2018 Morning
Oct. 30, 2018 4 rows of panels done
Oct. 31, 2018 starting the 5th row of panels
Oct. 31, 2018
Oct. 31, 2018 morning
Nov. 1, 2018 five rows done
Nov. 1, 2018 morning. One more row to go.
Nov. 1, 2018 sixth row going on
Nov. 2, 2018 All six rows done. Starting on the cross beams for the roof.
Nov. 5, 2018 morning. View inside the tank
Nov. 5, 2018 morning. Each beam is checked for scratches in the enamel using an electrical current, before it is put in place.
Nov. 6, 2018 morning. Roof going on.
Nov. 6, 2018 morning
Nov. 6, 2018 morning.
Nov. 6, 2018 tank level gauge going on.
Nov. 7, 2018 tank level gauge installed
Nov. 7, 2018 roof about completed looking from the inside
Nov. 7, 2018 looking up from inside the access hole.
Nov. 8, 2018 The Thompson Tank Crew L to R Gabriel, Joseph, Steven, Jose and George This crew gets it done!
Nov. 9, 2018 this is where the fill/use pipe hooks in
Nov. 15, 2018 tank filled to 7 feet checking for leaks
Nov. 16, 2018 tank filled to 14 feet. Taking longer than expected to fill.
Nov 16, 2018
Nov. 16, 2018

Nov. 20, 2018 on top of the tank.