Tank Demoliation and New Foundation Photo Gallery

Deepening the footing trench on one side after geotech investigation determined the soil was softer on that side. Sept. 14, 2018

One of two 6,900 gallon tanks being used to supply the town's water during tank construction. Sept. 14, 2018
Demolition of the old tank begins Sept. 4, 2018
Down she goes. Sept. 4, 2018
Footing trench ready for first concrete pour in the deeper section. Sept. 19, 2018
This side of the footing had to be dug much deeper to solid ground. Here it is after the first pour Sept. 21, 2018
Rebar for footing almost in place. Sept. 21, 2018.
Foundation form under construction Sept. 22, 2018
Foundation form under construction Sept. 22, 2018
Foundation form under construction Sept. 25, 2018
Foundation form under construction Sept. 25, 2018
Sept. 25, 2018 7:30 am
Sept. 28, 2018 7:30 am
Oct. 1, 2018 7:30 am
Oct. 1, 2018 7:30 am Getting the anchor bolts in place.
Oct. 2, 2018 1:10 pm The concrete is on its way.
Oct. 2, 2018 Starting the pour.
Oct. 2, 2018 Pouring concrete
Oct. 2, 2018 4:15 pm Pour done, crew still finishing up.
Oct. 3, 2018 The new tank sitting in the County Yard after delivery to Alleghany.
Oct. 8, 2018 The form being pulled off.
Oct. 8, 2018 The form pulled off. The center is being filled with road base which is being packed.
Oct. 9, 2018 7:15 am ready for tank construction
Oct. 9, 2018
Oct. 17, 2018 tank pad compacted. Tank crew will start to mobilize on Monday Oct. 22nd.